Industrial

CSC Facility

Redesigned vacant parcel with challenging mucky soil into a fully developed office and warehouse facility.
Location
Tampa, FL
Completed
May 2018
Starting Condition
Vacant parcel
Client
Caspers Cold Storage

Project Gallery

No items found.

Project Overview

In January 2016, work began on the CSC Facility for Caspers Cold Storage. The primary objective was to transform a vacant parcel of land by rezoning it to allow for the design, permitting, and construction of a brand-new office and warehouse development.

The development team faced several notable environmental obstacles during the project's early stages. They had to navigate a very wet site that contained environmentally sensitive areas, as well as deal with mucky soil situated directly where the new building was slated to be constructed.

To mitigate the settlement risk caused by the poor soil conditions, the team coordinated an overbearing of the building location with soil and monitored the site until the settling subsided. Once the stockpile was removed, the building was safely constructed, allowing the team to successfully deliver a fully developed office and warehouse facility by May 2018.

Project Details
Client
Caspers Cold Storage
Duration
2 Years
Starting Condition
Vacant parcel

Key Obstacles

• Very wet site

• Environmentally sensitive areas

• Mucky soil where the building was to be placed

Key Highlights and Wins

• Coordinated overbearing of the building location with soil which was monitored until the settling subsided. At that time the stockpile was removed, and the building could be constructed with minimal settlement risk.

Before
CAD Overlay
After